In the Shaping Department of Sheridan Company the unit materials cost is $6.00 and the unit conversion cost is $3.00. The department transferred out 41000 units and had 5400 units in ending work in process 25% complete. If all materials are added at the beginning of the process, the total cost to be assigned to the ending work in process is

Respuesta :

Answer:

$36,450

Explanation:

Calculating cost assigned to ending work in process:

Particulars                                                      Amount

Material (5,400 units*$6)                              $32,400

Conversion cost (5,400*25%*$3)                 $4,050  

Total cost of ending work in process         $36,450