Job 910 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 2,434 Direct labor-hours 72 labor-hours Direct labor wage rate $ 14 per labor-hour Machine-hours 132 machine-hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $15 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 910 would be:

Respuesta :

Answer:

$5,422

Explanation:

The computation of the total cost that should be recorded is shown below:

= Direct material cost + direct labor cost + manufacturing overhead cost

= $2,434 +  (72 labor hours × $14) +  (132 machine hours × $15)

= $2,434 + $1,008 + $1,980

= $5,422

hence, the total cost is $5,422