Answer:
The correct option is B.
The standard time for this job would be 12.10 minutes.
Explanation:
Element | St(min) | RF | AOT | NT
1 | 54.64 | 1.05 | 2.73 | 2.86
2 | 49.67 | 1.10 | 2.48 | 2.72
3 | 42.98 | 0.95 | 2.14 | 2.03
4 | 51.37 | 0.95 | 2.56 | 2.43
The standard time for the job is calculated by
Standard time = Total normal time*(1 + allowance factor)
Where Normal time is given by
Normal time = Average observation time * Rating Factor (RF)
Where Average observation time is given by
Average observation time = St(min)/number of job cycles
number of job cycles = 20
Total Normal time = 2.86 + 2.72 + 2.03 + 2.43
Total Normal time = 10.04 minutes
Standard time = 10.04*(1 + 0.20)
Standard time = 12.04 minutes
Therefore, the correct option would be B, the standard time for this job would be 12.10 minutes.