Which of the following is on the critical path of the planned schedule (in other words, disregard any hypothetical scenarios from questions 7 through 9):
(a) Form Sidewalks,
(b) Pour Sidewalks,
(c) Plant Trees & Shrubs,
(d) Concrete Curbs.